Immediate Fixes for Heavy Traffic
About 34,000 drivers travel Lee Drive each day. Poor pavement conditions along this route cause vehicle damage and liability claims. Consequently, Fred Raiford leads phased repairs to smooth the ride now. Crews target rough patches near the Bayou Duplantier bridge and Liberty High School. Additionally, drivers can expect work to finish around the first or second week of December.
Communicating With Local Residents
Fred Raiford met with homeowners associations to explain the short-term plan. Previously, rattling cars created noisy conditions for nearby houses. Therefore, crews smooth the surface to cut down on daily noise and bumps. Furthermore, workers tie driveways into the street cleanly so homeowners enter and exit smoothly.
Planning the Full Widening Project
A major widening of Lee Drive sits roughly a year and a half away. First, crews acquire right-of-way and relocate utilities along the corridor. Next, teams tackle construction in two phases between Highland Road and Perkins Road. Because nearby schools and businesses rely on steady access, full closures remain off the table. Ultimately, phased work helps drivers get around safely while crews build a better road.